GE19 bridge
|
|
We demolished and removed the Bridge GE19 over the main possession of 6 rail lines into Liverpool Street running to the country and back during 22nd Dec-30th Dec 2007.
The works were on behalf of J Murphy & Sons (MG) the principle contractor for Network Rail.
The program was scheduled for 6 days but was actually achieved in 4 days.
|
|
|
|
|